Home > Articles

This chapter is from the book

Planning a Project

The PMBOK® Guide, Sixth Edition, discusses planning in the planning process group. The PMBOK® Guide, Seventh Edition, discusses planning in the Planning Performance domain.

Planning is the foundation for all project success. Many projects fail due to inadequate planning. Planning is considered one of the critical steps toward project success because it provides the structure and foresight for the execution and monitoring steps of a project. It is an essential guide for the project manager, project teams, stakeholders, and sponsors to achieve successful completion of each stage of the project.

However, there are different levels of planning based on the size and nature of the project and the development approach. In predictive projects, detail planning is done at the beginning of the project, and any changes to the plan need to be constrained and go through a change control process. In agile, only a high-level “relative estimate” is made at the beginning of the project, with the detailed estimates performed per sprint.

Per the PMBOK® Guide, Seventh Edition, “the Planning Performance domain addresses the activities and functions associated with the initial, ongoing, and evolving organization and coordination necessary for delivering project deliverables and outcomes.”

Throughout the planning process, the project manager must consider internal and external factors that could impact the project. The PM needs to identify assumptions and constraints that could lead to uncertainty and risks on the project. The project manager also needs to progressively elaborate on projects to ensure correct ranges are calculated and management plans are updated. However, planning also needs to be an efficient process. If there are many unknowns and many uncertainties on a project (risks), it is challenging to perform detailed planning of the scope. In this case, more time should be spent on planning for risk, and the scope should be progressively elaborated over time. The project manager and the project team determine the exact parameters of planning.

Some of the key points regarding planning are that

  • Time spent on planning should be appropriate for the project. It is very easy to “overplan” when there are many uncertain parameters that impact the project. Likewise, not enough planning may lead to issues and problems during delivery.

  • Planning is sufficient to deliver value and manage stakeholders’ expectations. The purpose of a project is to deliver value for the customer, so the project manager and/or team must plan sufficiently to deliver the value. The exact meaning of value differs based on many parameters, such as the nature of the project, the stakeholders, and the industry. This issue is discussed in more detail later in the “Executing the Project” section of this chapter.

  • Project plans are progressively elaborated on throughout the project life cycle to adapt to changes as needed. This is true for both predictive and adaptive projects. A change to one project constraint may lead to a change in another constraint, so plans need to be able to adapt (even on predictive projects).

Variables that impact project planning can include

  • Development Approach

    • Based on whether this is a predictive, adaptive, incremental, iterative, or hybrid project, this approach can influence how much planning and the type of planning that needs to be done.

    • You might need to plan phases, iterations, increments, or sprints.

  • Project Deliverables: The product or service that is being delivered determines the type and extent of planning. For example, a construction project requires extensive planning to minimize scope changes, whereas the scope of research and development projects can be dynamic.

  • Organizational Requirements: The company’s governance, policies, procedures, and culture determine project planning procedures.

  • Market Conditions: External factors such as scarcity of resources and competition determine the level of planning that needs to be performed. If, for example, a competitor is releasing a superior product to yours, the schedule for your upgrade project may need to be moved forward, thus impacting planning.

  • Legal or Regulatory Requirements: Your project might need regular approvals from regulatory authorities before proceeding to the next stage. This step needs to be planned, but any delays need adjustment to the schedule and plans. For example, construction projects require inspections at various stages. If the inspector doesn’t approve the deliverable, it needs to be fixed before the building team can continue to the next stage.

The PMBOK® Guide, Sixth Edition, defines the planning process group as consisting of the processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project was undertaken to achieve.

Twenty-four processes in the PMBOK® Guide, Sixth Edition, process map are associated with the planning process group, as shown in Table 4-3. There are 49 processes altogether in the entire process map, and almost half of them are in planning, showing that PMI has placed a huge emphasis on planning a project.

Table 4-3 PMBOK Guide, Sixth Edition, Knowledge Areas and Processes Associated with the Planning Process Group

Knowledge Area

Planning Processes

Project Integration Management

Develop Project Management Plan

Project Scope Management

Plan Scope Management

Collect Requirements

Define Scope

Create WBS (Work Breakdown Structure)

Project Schedule Management

Plan Schedule Management

Define Activities

Sequence Activities

Estimate Activity Durations

Develop Schedule

Project Cost Management

Plan Cost Management

Estimate Cost

Determine Budget

Project Quality Management

Plan Quality Management

Project Resources Management

Plan Resource Management

Estimate Activity Resources

Project Communications Management

Plan Communications Management

Project Risk Management

Plan Risk Management

Identify Risks

Perform Qualitative Risk Analysis

Perform Quantitative Risk Analysis

Plan Risk Responses

Project Procurement Management

Plan Procurement Management

Project Stakeholder Management

Plan Stakeholder Management

In this chapter, we concentrate on the integration management aspects of planning. The other planning processes are discussed in the appropriate chapters related to those knowledge area topics.

The PMBOK® Guide, Sixth Edition, planning process for integration management is called Develop Project Management Plan, which includes the plans for all the other knowledge areas.

Table 4-4 highlights the PMBOK® Guide, Sixth Edition, process that we describe in this section.

Table 4-4 PMBOK® Guide, Sixth Edition, Develop Project Management Plan

Process Group Knowledge Area

Initiating

Planning

Executing

Monitoring and Controlling

Closing

4.0 Project Integration Management

4.1 Develop Project Charter

4.2 Develop Project Management Plan

4.3 Direct and Manage Project Work

4.4 Manage Project Knowledge

4.5 Monitor and Control Project Work

4.6 Perform Integrated Change Control

4.7 Close Project or Phase

The Project Management Plan is made up of many planning documents (artifacts), as follows:

key_topic_icon.jpg
  • Subsidiary Management Plans, which include

    • Scope Management Plan

    • Requirements Management Plan

    • Schedule Management Plan

    • Cost Management Plan

    • Quality Management Plan

    • Resource Management Plan

    • Communications Management Plan

    • Risk Management Plan

    • Procurement Management Plan

    • Stakeholder Engagement Plan

  • Baselines, which include

    • Scope Baseline

    • Schedule Baseline

    • Cost Baseline

  • Additional Components, which include

    • Change Management Plan

    • Configuration Management Plan

    • Performance Measurement Baseline

    • Project Life Cycle

    • Development Approach

    • Management Review

Understanding the purpose of each of the components of the project management plan is important, so let’s discuss each of these components.

key_topic_icon.jpg

Subsidiary Management Plans

Each of the subsidiary management plans documents how you are to plan, execute, manage, and control the respective knowledge area. They do not contain the actual results of that knowledge area.

For example, the requirements management plan does not contain any requirements. It documents the procedures for collecting requirements. It documents how you are going to collect requirements, what tools you are going to use to collect requirements, and the level of details you need to collect requirements. It also documents procedures for missed requirements and procedures for adding new requirements.

Likewise, the cost management plan does not tell you what the project is going to cost. It documents how you are going to estimate cost, the formulae used, the assumptions made, and the procedures for trying to get back on track if you start to go over budget.

All subsidiary management plans document procedures on how to plan, execute, manage, and control each particular knowledge area.

The only subsidiary management plan that does not have the words management plan in the title is the stakeholder engagement plan. However, it, too, documents procedures on how to engage and motivate stakeholders.

It’s also important to understand that a project manager does not know all these procedures at the beginning of the project. The project manager must work with the project team to figure out all these procedures throughout the project and progressively elaborate on the plan documents as necessary.

key_topic_icon.jpg

Baselines

A baseline is simply the approved version of a plan. Plans need to be approved by appropriate stakeholders, such as the project manager, sponsor, project leadership team, and key members of the project team. During planning, the project manager, senior management, and other key stakeholders determine who will have such approval responsibilities.

The three basic baselines—the scope baseline, schedule baseline, and cost baseline—represent the approved versions of the scope, schedule, and budget, respectively. In addition, a fourth baseline, the performance measurement baseline, represents these three basic baselines combined.

These baselines represent the plan for the project, and actual results are compared against the baselines. However, the main significance of the baselines is that any changes to the baselines must go through a change control process.

On predictive projects, changes must be properly controlled, so changes always need to go through a change control process.

  • The work of the project is executed according to the baseline.

  • Actual results are compared to the baseline.

  • Subsequent changes must go through the change control process.

  • Project may be re-baselined after sign-off from appropriate stakeholders.

On pure agile projects, there are no baselines. The scope of the work is determined by the product backlog, which will change as user stories are added, removed, and reprioritized.

key_topic_icon.jpg

Additional Components

Two additional management plans and an additional baseline are listed under this subsection, as follows:

  • Change Management Plan: Documents the procedures for change control.

  • Configuration Management Plan: Documents procedures regarding version control.

  • Performance Measurement Baseline: This artifact is a combination of the scope, schedule, and cost baselines.

Three other documents listed in this section are

  • Project Life Cycle: Discussed in Chapter 3, “Development Approach and Life Cycle Performance,” these are the series of stages a project goes through from start to finish.

  • Development Approach: This document identifies the approaches used, such as predictive, agile/adaptive, iterative, incremental, or hybrid.

  • Management Review: This document provides the points on the project where appropriate stakeholders will review project progress and make appropriate decisions.

key_topic_icon.jpg

Table 4-5 is an extract of the PMBOK® Guide, Sixth Edition, process map highlighting the planning group and the processes referred to in the preceding exam tip.

Table 4-5 PMBOK® Guide, Sixth Edition, Processes in Planning

Process Group Knowledge Area

Initiating

Planning

4.0 Project Integration Management

4.1 Develop Project Charter

4.2 Develop Project Management Plan

5.0 Project Scope Management

 

5.1 Plan Scope Management

5.2 Collect Requirements

5.3 Define Scope

5.4 Create WBS

6.0 Project Schedule Management

 

6.1 Plan Schedule Management

6.2 Define Activities

6.3 Sequence Activities

6.4 Estimate Activity Durations

6.5 Develop Schedule

7.0 Project Cost Management

 

7.1 Plan Cost Management

7.2 Estimate Costs

7.3 Determine Budget

8.0 Project Quality Management

 

8.1 Plan Quality Management

9.0 Project Resource Management

 

9.1 Plan Resource Management

9.2 Estimate Activity Resources

10.0 Project Communications Management

 

10.1 Plan Communications Management

11.0 Project Risk Management

 

11.1 Plan Risk Management

11.2 Identify Risks

11.3 Perform Qualitative Risk Analysis

11.4 Perform Quantitative Risk Analysis

11.5 Plan Risk Responses

12.0 Project Procurement Management

 

12.1 Plan Procurement Management

13.0 Project Stakeholder Management

13.1 Identify Stakeholders

13.2 Plan Stakeholder Engagement

Pearson IT Certification Promotional Mailings & Special Offers

I would like to receive exclusive offers and hear about products from Pearson IT Certification and its family of brands. I can unsubscribe at any time.

Overview


Pearson Education, Inc., 221 River Street, Hoboken, New Jersey 07030, (Pearson) presents this site to provide information about Pearson IT Certification products and services that can be purchased through this site.

This privacy notice provides an overview of our commitment to privacy and describes how we collect, protect, use and share personal information collected through this site. Please note that other Pearson websites and online products and services have their own separate privacy policies.

Collection and Use of Information


To conduct business and deliver products and services, Pearson collects and uses personal information in several ways in connection with this site, including:

Questions and Inquiries

For inquiries and questions, we collect the inquiry or question, together with name, contact details (email address, phone number and mailing address) and any other additional information voluntarily submitted to us through a Contact Us form or an email. We use this information to address the inquiry and respond to the question.

Online Store

For orders and purchases placed through our online store on this site, we collect order details, name, institution name and address (if applicable), email address, phone number, shipping and billing addresses, credit/debit card information, shipping options and any instructions. We use this information to complete transactions, fulfill orders, communicate with individuals placing orders or visiting the online store, and for related purposes.

Surveys

Pearson may offer opportunities to provide feedback or participate in surveys, including surveys evaluating Pearson products, services or sites. Participation is voluntary. Pearson collects information requested in the survey questions and uses the information to evaluate, support, maintain and improve products, services or sites; develop new products and services; conduct educational research; and for other purposes specified in the survey.

Contests and Drawings

Occasionally, we may sponsor a contest or drawing. Participation is optional. Pearson collects name, contact information and other information specified on the entry form for the contest or drawing to conduct the contest or drawing. Pearson may collect additional personal information from the winners of a contest or drawing in order to award the prize and for tax reporting purposes, as required by law.

Newsletters

If you have elected to receive email newsletters or promotional mailings and special offers but want to unsubscribe, simply email information@informit.com.

Service Announcements

On rare occasions it is necessary to send out a strictly service related announcement. For instance, if our service is temporarily suspended for maintenance we might send users an email. Generally, users may not opt-out of these communications, though they can deactivate their account information. However, these communications are not promotional in nature.

Customer Service

We communicate with users on a regular basis to provide requested services and in regard to issues relating to their account we reply via email or phone in accordance with the users' wishes when a user submits their information through our Contact Us form.

Other Collection and Use of Information


Application and System Logs

Pearson automatically collects log data to help ensure the delivery, availability and security of this site. Log data may include technical information about how a user or visitor connected to this site, such as browser type, type of computer/device, operating system, internet service provider and IP address. We use this information for support purposes and to monitor the health of the site, identify problems, improve service, detect unauthorized access and fraudulent activity, prevent and respond to security incidents and appropriately scale computing resources.

Web Analytics

Pearson may use third party web trend analytical services, including Google Analytics, to collect visitor information, such as IP addresses, browser types, referring pages, pages visited and time spent on a particular site. While these analytical services collect and report information on an anonymous basis, they may use cookies to gather web trend information. The information gathered may enable Pearson (but not the third party web trend services) to link information with application and system log data. Pearson uses this information for system administration and to identify problems, improve service, detect unauthorized access and fraudulent activity, prevent and respond to security incidents, appropriately scale computing resources and otherwise support and deliver this site and its services.

Cookies and Related Technologies

This site uses cookies and similar technologies to personalize content, measure traffic patterns, control security, track use and access of information on this site, and provide interest-based messages and advertising. Users can manage and block the use of cookies through their browser. Disabling or blocking certain cookies may limit the functionality of this site.

Do Not Track

This site currently does not respond to Do Not Track signals.

Security


Pearson uses appropriate physical, administrative and technical security measures to protect personal information from unauthorized access, use and disclosure.

Children


This site is not directed to children under the age of 13.

Marketing


Pearson may send or direct marketing communications to users, provided that

  • Pearson will not use personal information collected or processed as a K-12 school service provider for the purpose of directed or targeted advertising.
  • Such marketing is consistent with applicable law and Pearson's legal obligations.
  • Pearson will not knowingly direct or send marketing communications to an individual who has expressed a preference not to receive marketing.
  • Where required by applicable law, express or implied consent to marketing exists and has not been withdrawn.

Pearson may provide personal information to a third party service provider on a restricted basis to provide marketing solely on behalf of Pearson or an affiliate or customer for whom Pearson is a service provider. Marketing preferences may be changed at any time.

Correcting/Updating Personal Information


If a user's personally identifiable information changes (such as your postal address or email address), we provide a way to correct or update that user's personal data provided to us. This can be done on the Account page. If a user no longer desires our service and desires to delete his or her account, please contact us at customer-service@informit.com and we will process the deletion of a user's account.

Choice/Opt-out


Users can always make an informed choice as to whether they should proceed with certain services offered by Adobe Press. If you choose to remove yourself from our mailing list(s) simply visit the following page and uncheck any communication you no longer want to receive: www.pearsonitcertification.com/u.aspx.

Sale of Personal Information


Pearson does not rent or sell personal information in exchange for any payment of money.

While Pearson does not sell personal information, as defined in Nevada law, Nevada residents may email a request for no sale of their personal information to NevadaDesignatedRequest@pearson.com.

Supplemental Privacy Statement for California Residents


California residents should read our Supplemental privacy statement for California residents in conjunction with this Privacy Notice. The Supplemental privacy statement for California residents explains Pearson's commitment to comply with California law and applies to personal information of California residents collected in connection with this site and the Services.

Sharing and Disclosure


Pearson may disclose personal information, as follows:

  • As required by law.
  • With the consent of the individual (or their parent, if the individual is a minor)
  • In response to a subpoena, court order or legal process, to the extent permitted or required by law
  • To protect the security and safety of individuals, data, assets and systems, consistent with applicable law
  • In connection the sale, joint venture or other transfer of some or all of its company or assets, subject to the provisions of this Privacy Notice
  • To investigate or address actual or suspected fraud or other illegal activities
  • To exercise its legal rights, including enforcement of the Terms of Use for this site or another contract
  • To affiliated Pearson companies and other companies and organizations who perform work for Pearson and are obligated to protect the privacy of personal information consistent with this Privacy Notice
  • To a school, organization, company or government agency, where Pearson collects or processes the personal information in a school setting or on behalf of such organization, company or government agency.

Links


This web site contains links to other sites. Please be aware that we are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of each and every web site that collects Personal Information. This privacy statement applies solely to information collected by this web site.

Requests and Contact


Please contact us about this Privacy Notice or if you have any requests or questions relating to the privacy of your personal information.

Changes to this Privacy Notice


We may revise this Privacy Notice through an updated posting. We will identify the effective date of the revision in the posting. Often, updates are made to provide greater clarity or to comply with changes in regulatory requirements. If the updates involve material changes to the collection, protection, use or disclosure of Personal Information, Pearson will provide notice of the change through a conspicuous notice on this site or other appropriate way. Continued use of the site after the effective date of a posted revision evidences acceptance. Please contact us if you have questions or concerns about the Privacy Notice or any objection to any revisions.

Last Update: November 17, 2020