- Understanding PMI's Planning Process Group
- Integration Management
- Scope Management
- Activity Planning?From WBS to Project Schedule
- Project Cost Estimating Factors
- What Next?
Project Cost Estimating Factors
- Plan Cost Management—7.1
- Estimate Costs—7.2
- Determine Budget—7.3
Plan Cost Management
The first process in the cost management knowledge area is plan cost management. This process defines the policies and procedures for planning, managing, and controlling project costs. This process provides guidance on how costs will be managed throughout the project, taking into account stakeholder requirements for managing costs. All of the subsequent processes in the cost management knowledge area depend on the plan developed in this process. Table 4.13 shows the inputs, tools and techniques, and outputs for the plan cost management process.
TABLE 4.13 Plan Cost Management Inputs, Tools and Techniques, and Outputs
Inputs |
Tools and Techniques |
Outputs |
Project management plan |
Expert judgment |
Cost management plan |
Project charter |
Analytical techniques |
|
Enterprise environmental factors |
Meetings |
|
Organizational process assets |
Estimate Costs
The estimate cost process associates an expected cost of performing work to each activity. Cost estimates can include labor, materials, equipment, and any other direct costs for project activities. Based on the activity resource and duration estimates, the cost estimates express the cost, normally in monetary amounts, of completing the work of the project. As with all other project documents, the cost estimates can change through the project as conditions change. Different events can cause the cost for any activity to go up or down and may require the cost estimates for the project to change. Table 4.14 shows the inputs, tools and techniques, and outputs for the estimate cost process.
TABLE 4.14 Estimate Cost Inputs, Tools and Techniques, and Outputs
Inputs |
Tools and Techniques |
Outputs |
Cost management plan |
Expert judgment |
Activity cost estimates |
Human resource management plan |
Analogous estimating |
Basis of estimates |
Scope baseline |
Parametric estimating |
Project documents updates |
Project schedule |
Bottom-up estimating |
|
Risk register |
Three-point estimating |
|
Enterprise environmental factors |
Reserve analysis |
|
Organizational process assets |
Cost of quality |
|
Project management software |
||
Vendor bid analysis |
||
Group decision-making |
Cost estimates are compiled into the project budget. You probably recognize several estimating techniques from other processes. Three of the techniques used in the estimate costs process are the same basic techniques used in the estimate activity durations process. The other technique, bottom-up estimating, is also used in the estimate activity resources process. Although they are the same techniques, they are applied to different criteria and bear revisiting.
- Analogous estimating—This uses actual cost values from similar activities. These activities can be from the same project or another project.
- Parametric estimating—This calculates cost estimates by multiplying the quantity of work or result of work, such as square feet or hours, by a known rate, such as $30 per square foot or $45 per hour. This type of estimate works best for standardized, and often repeated, activities.
Three-point estimating—This uses three estimate values for each activity:
- Most likely—The cost most likely to occur
- Optimistic—The cost of the activity if everything goes as planned, or better
- Pessimistic—The cost of the activity in a worst-case scenario
- Bottom-up estimating—This technique calculates cost estimates by adding the costs of each individual work package. The technique starts at the most detailed level and rolls up the costs until a total cost for the project is obtained.
Determine Budget
After you know the costs to accomplish the work of the project, you can create the project budget. The determine budget process aggregates the activity cost estimates into a single document for the project. The resulting project budget expands on the preliminary budget from the project charter and provides far more detail. Table 4.15 shows the inputs, tools and techniques, and outputs for the determine budget process.
TABLE 4.15 Determine Budget Inputs, Tools and Techniques, and Outputs
Inputs |
Tools and Techniques |
Outputs |
Cost management plan |
Cost aggregation |
Cost baseline |
Scope baseline |
Reserve analysis |
Project funding requirements |
Activity cost estimates |
Expert judgment |
Project documents updates |
Basis of estimates |
Historical relationships |
|
Project schedule |
Funding limit reconciliation |
|
Resource calendars |
||
Risk register |
||
Agreements |
||
Organizational process assets |